HomeMy WebLinkAboutO-3770-9-20 ORDINANCE NO. 3770-9-20
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF ALLEN, COLLIN
COUNTY,TEXAS,APPROVING A NEGOTIATED SETTLEMENT BETWEEN THE
ATMOS CITIES STEERING COMMITTEE ("ACSC") AND ATMOS ENERGY
CORP.,MID-TEX DIVISION REGARDING THE COMPANY'S 2020 RATE REVIEW
MECHANISM FILING;DECLARING EXISTING RATES TO BE UNREASONABLE;
ADOPTING TARIFFS THAT REFLECT RATE ADJUSTMENTS CONSISTENT
WITH THE NEGOTIATED SETTLEMENT; FINDING THE RATES TO BE SET BY
THE ATTACHED SETTLEMENT TARIFFS TO BE JUST AND REASONABLE AND
IN THE PUBLIC INTEREST; APPROVING AN ATTACHED EXHIBIT
ESTABLISHING A BENCHMARK FOR PENSIONS AND RETIREE MEDICAL
BENEFITS; APPROVING AN ATTACHED EXHIBIT REGARDING
AMORTIZATION OF REGULATORY LIABILITY; REQUIRING THE COMPANY
TO REIMBURSE ACSC'S REASONABLE RATEMAKING EXPENSES;
DETERMINING THAT THIS ORDINANCE WAS PASSED IN ACCORDANCE WITH
THE REQUIREMENTS OF THE TEXAS OPEN MEETINGS ACT; ADOPTING A
SAVINGS CLAUSE; DECLARING AN EFFECTIVE DATE; AND REQUIRING
DELIVERY OF THIS ORDINANCE TO THE COMPANY AND THE ACSC'S LEGAL
COUNSEL.
WHEREAS, the City of Allen, Texas ("City") is a gas utility customer of Atmos Energy Corp., Mid-Tex
Division("Atmos Mid-Tex" or"Company"), and a regulatory authority with an interest in the rates, charges,
and services of Atmos Mid-Tex; and,
WHEREAS,the City is a member of the Atmos Cities Steering Committee("ACSC"),a coalition of similarly-
situated cities served by Atmos Mid-Tex ("ACSC Cities")that have joined together to facilitate the review of,
and response to,natural gas issues affecting rates charged in the Atmos Mid-Tex service area; and,
WHEREAS,ACSC and the Company worked collaboratively to develop a Rate Review Mechanism("RRM")
tariff that allows for an expedited rate review process by ACSC Cities as a substitute to the Gas Reliability
Infrastructure Program("GRIP")process instituted by the Legislature,and that will establish rates for the ACSC
Cities based on the system-wide cost of serving the Atmos Mid-Tex Division; and,
WHEREAS,the current RRM tariff was adopted by the City in a rate ordinance in 2019; and,
WHEREAS, on about March 31, 2020, Atmos Mid-Tex filed its 2020 RRM rate request with ACSC Cities
based on a test year ending December 31,2019; and,
WHEREAS, ACSC coordinated its review of the Atmos Mid-Tex 2020 RRM filing through its Executive
Committee, assisted by ACSC's attorneys and consultants,to resolve issues identified in the Company's RRM
filing; and,
WHEREAS, the Executive Committee, as well as ACSC's counsel and consultants, recommend that ACSC
Cities approve an increase in base rates for Atmos Mid-Tex of$90 million applicable to ACSC Cities with an
Effective Date of December 1, 2020; and,
WHEREAS, ACSC agrees that Atmos plant-in-service is reasonable; and,
WHEREAS, with the exception of approved plant-in-service, ACSC is not foreclosed from future
reasonableness evaluation of costs associated with incidents related to gas leaks; and,
WHEREAS,the two month delayed Effective Date from October 1 to December 1 will save ACSC ratepayers
approximately $9 million off new rates imposed by the attached tariffs (Exhibit A), the impact on ratepayers
should approximate the reasonable value of the rate filing found by the ACSC Consultants' Report,which was
$81 million; and,
WHEREAS, the attached tariffs (Exhibit A) implementing new rates are consistent with the recommendation
of the ACSC Executive Committee, are agreed to by the Company, and are just, reasonable, and in the public
interest; and,
WHEREAS,the settlement agreement sets a new benchmark for pensions and retiree medical benefits(Exhibit
B); and,
WHEREAS,the settlement agreement establishes an amortization schedule for regulatory liability prepared by
Atmos Mid-Tex(Exhibit C); and,
WHEREAS, the RRM Tariff contemplates reimbursement of ACSC's reasonable expenses associated with
RRM applications;
NOW,THEREFORE,BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF ALLEN,
COLLIN COUNTY,TEXAS,THAT:
SECTION 1. The findings set forth in this Ordinance are hereby in all things approved.
SECTION 2. Without prejudice to future litigation of any issue identified by ACSC, the City Council fmds
that the settled amount of an increase in revenues of$90 million for ACSC Cities represents a comprehensive
settlement of gas utility rate issues affecting the rates, operations, and services offered by Atmos Mid-Tex
within the municipal limits arising from Atmos Mid-Tex's 2020 RRM filing, is in the public interest, and is
consistent with the City's authority under Section 103.001 of the Texas Utilities Code.
SECTION 3. Despite finding Atmos Mid-Tex's plant-in-service to be reasonable, ACSC is not foreclosed in
future cases from evaluating the reasonableness of costs associated with incidents involving leaks of natural
gas.
SECTION 4. The existing rates for natural gas service provided by Atmos Mid-Tex are unreasonable. The
new tariffs attached hereto and incorporated herein as Exhibit A, are just and reasonable, and are designed to
allow Atmos Mid-Tex to recover annually an additional $90 million from customers in ACSC Cities, over the
amount allowed under currently approved rates. Such tariffs are hereby adopted.
SECTION 5. The ratemaking treatment for pensions and retiree medical benefits in Atmos Mid-Tex's next
RRM filing shall be as set forth on Exhibit B, attached hereto and incorporated herein.
SECTION 6. Subject to any future settlement or decision regarding the balance of Excess Deferred Income
Tax to be refunded to ratepayers, the amortization of regulatory liability shall be consistent with the schedule
found in Exhibit C, attached hereto and incorporated herein.
SECTION 7. Atmos Mid-Tex shall reimburse the reasonable ratemaking expenses of the ACSC in processing
the Company's 2020 RRM filing.
SECTION 8. To the extent any resolution or ordinance previously adopted by the Council is inconsistent with
this Ordinance,it is hereby repealed.
Ordinance No.3770-9-20,Page 2
SECTION 9. The meeting at which this Ordinance was approved was in all things conducted in strict
compliance with the Texas Open Meetings Act, Texas Government Code,Chapter 551.
SECTION 10. If any one or more sections or clauses of this Ordinance is adjudged to be unconstitutional or
invalid, such judgment shall not affect, impair, or invalidate the remaining provisions of this Ordinance, and
the remaining provisions of the Ordinance shall be interpreted as if the offending section or clause never existed.
SECTION 11. Consistent with the City Ordinance that established the RRM process, this Ordinance shall
become effective from and after its passage with rates authorized by attached tariffs to be effective for bills
rendered on or after December 1,2020.
SECTION 12. A copy of this Ordinance shall be sent to Atmos Mid-Tex, care of Chris Felan,Vice President
of Rates and Regulatory Affairs Mid-Tex Division,Atmos Energy Corporation,5420 LBJ Freeway,Suite 1862,
Dallas, Texas 75240, and to Geoffrey Gay, General Counsel to ACSC, at Lloyd Gosselink Rochelle &
Townsend,P.C., 816 Congress Avenue, Suite 1900,Austin, Texas 78701.
DULY PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF ALLEN,COLLIN
COUNTY,TEXAS, ON THIS THE 8TH DAY OF SEPTEMBER 2020.
APP D:
Deb 'e Stout,MAYOR
APPROVED AS TO FORM: ATTEST:
Peter G.Smitig CITY ATTORNEY Sh y B.George, Y SECRETARY
Ordinance No.3770-9-20,Page 3
I
Exhibit A
to 2020 RRM Resolution or Ordinance
Mid-Tex Tariffs
Effective December 1, 2020
I
I
Ordinance No.3770-9-20,Page 4
MID-TEX DIVISION RRC Tariff No:
ATMOS ENERGY CORPORATION
RATE SCHEDULE: R—RESIDENTIAL SALES
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 PAGE:
Application
Applicable to Residential Customers for all natural gas provided at one Point of Delivery and measured
through one meter.
Type of Service
Where service of the type desired by Customer is not already available at the Point of Delivery, additional
charges and special contract arrangements between Company and Customer may be required prior to
service being furnished.
Monthly Rate
Customer's monthly bill will be calculated by adding the following Customer and Ccf charges to the
amounts due under the riders listed below:
Charge Amount
Customer Charge per Bill $20.25 per month
Rider CEE Surcharge $ 0.05 per month'
Total Customer Charge $20.30 per month
Commodity Charge—All Ccf $0.26651 per Ccf
Gas Cost Recovery: Plus an amount for gas costs and upstream transportation costs calculated
in accordance with Part(a) and Part(b), respectively, of Rider GCR.
Weather Normalization Adjustment: Plus or Minus an amount for weather normalization
calculated in accordance with Rider WNA.
Franchise Fee Adjustment: Plus an amount for franchise fees calculated in accordance with Rider
FF. Rider FF is only applicable to customers inside the corporate limits of any incorporated
municipality.
Tax Adjustment: Plus an amount for tax calculated in accordance with Rider TAX.
Surcharges: Plus an amount for surcharges calculated in accordance with the applicable rider(s).
Agreement
An Agreement for Gas Service may be required.
Notice
Service hereunder and the rates for services provided are subject to the orders of regulatory bodies
having jurisdiction and to the Company's Tariff for Gas Service.
'Reference Rider CEE-Conservation and Energy Efficiency as approved in GUD 10170. Surcharge billing effective July 1,2020.
Ordinance No. 3770-9-20, Page 5
MID-TEX DIVISION RRC Tariff No:
ATMOS ENERGY CORPORATION
RATE SCHEDULE: C—COMMERCIAL SALES
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 PAGE:
Application
Applicable to Commercial Customers for all natural gas provided at one Point of Delivery and measured
through one meter and to Industrial Customers with an average annual usage of less than 30,000 Ccf.
Type of Service
Where service of the type desired by Customer is not already available at the Point of Delivery, additional
charges and special contract arrangements between Company and Customer may be required prior to
service being furnished.
Monthly Rate
Customer's monthly bill will be calculated by adding the following Customer and Ccf charges to the
amounts due under the riders listed below:
Charge Amount
Customer Charge per Bill $ 54.50 per month
Rider CEE Surcharge $ 0.02 per month'
Total Customer Charge $ 54.52 per month
Commodity Charge—All Ccf $0.11728 per Ccf
Gas Cost Recovery: Plus an amount for gas costs and upstream transportation costs calculated
in accordance with Part(a) and Part(b), respectively, of Rider GCR.
Weather Normalization Adjustment: Plus or Minus an amount for weather normalization
calculated in accordance with Rider WNA.
Franchise Fee Adjustment: Plus an amount for franchise fees calculated in accordance with Rider
FF. Rider FF is only applicable to customers inside the corporate limits of any incorporated
municipality.
Tax Adjustment: Plus an amount for tax calculated in accordance with Rider TAX.
Surcharges: Plus an amount for surcharges calculated in accordance with the applicable rider(s).
Agreement
An Agreement for Gas Service may be required.
Notice
Service hereunder and the rates for services provided are subject to the orders of regulatory bodies
having jurisdiction and to the Company's Tariff for Gas Service.
Reference Rider CEE-Conservation and Energy Efficiency as approved in GUD 10170. Surcharge billing effective July 1,2020.
Ordinance No. 3770-9-20, Page 6
MID-TEX DIVISION RRC Tariff No:
ATMOS ENERGY CORPORATION
RATE SCHEDULE: I—INDUSTRIAL SALES
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/0112020 PAGE:
Application
Applicable to Industrial Customers with a maximum daily usage (MDU) of less than 3,500 MMBtu per day
for all natural gas provided at one Point of Delivery and measured through one meter. Service for
Industrial Customers with an MDU equal to or greater than 3,500 MMBtu per day will be provided at
Company's sole option and will require special contract arrangements between Company and Customer.
Type of Service
Where service of the type desired by Customer is not already available at the Point of Delivery, additional
charges and special contract arrangements between Company and Customer may be required prior to
service being furnished.
Monthly Rate
Customer's monthly bill will be calculated by adding the following Customer and MMBtu charges to the
amounts due under the riders listed below:
Charge Amount
Customer Charge per Meter $ 1,014.50 per month
First 0 MMBtu to 1,500 MMBtu $0.4157 per MMBtu
Next 3,500 MMBtu $0.3044 per MMBtu
All MMBtu over 5,000 MMBtu $0.0653 per MMBtu
Gas Cost Recovery: Plus an amount for gas costs and upstream transportation costs calculated
in accordance with Part(a)and Part(b), respectively, of Rider GCR.
Franchise Fee Adjustment: Plus an amount for franchise fees calculated in accordance with Rider
FF. Rider FF is only applicable to customers inside the corporate limits of any incorporated
municipality.
Tax Adjustment: Plus an amount for tax calculated in accordance with Rider TAX.
Surcharges: Plus an amount for surcharges calculated in accordance with the applicable rider(s).
Curtailment Overpull Fee
Upon notification by Company of an event of curtailment or interruption of Customer's deliveries,
Customer will, for each MMBtu delivered in excess of the stated level of curtailment or interruption, pay
Company 200% of the midpoint price for the Katy point listed in Platts Gas Daily published for the
applicable Gas Day in the table entitled "Daily Price Survey."
Replacement Index
In the event the "midpoint" or "common" price for the Katy point listed in Platts Gas Daily in the table
entitled "Daily Price Survey" is no longer published, Company will calculate the applicable imbalance fees
utilizing a daily price index recognized as authoritative by the natural gas industry and most closely
approximating the applicable index.
Ordinance No. 3770-9-20, Page 7
MID-TEX DIVISION RRC Tariff No:
ATMOS ENERGY CORPORATION
RATE SCHEDULE: I—INDUSTRIAL SALES
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 PAGE:
Agreement
An Agreement for Gas Service may be required.
Notice
Service hereunder and the rates for services provided are subject to the orders of regulatory bodies
having jurisdiction and to the Company's Tariff for Gas Service.
Special Conditions
In order to receive service under Rate I, Customer must have the type of meter required by Company.
Customer must pay Company all costs associated with the acquisition and installation of the meter.
Ordinance No. 3770-9-20, Page 8
MID-TEX DIVISION RRC Tariff No:
ATMOS ENERGY CORPORATION
RATE SCHEDULE: T—TRANSPORTATION
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 1 PAGE:
Application
Applicable, in the event that Company has entered into a Transportation Agreement, to a customer
directly connected to the Atmos Energy Corp., Mid-Tex Division Distribution System (Customer) for the
transportation of all natural gas supplied by Customer or Customer's agent at one Point of Delivery for
use in Customer's facility.
Type of Service
Where service of the type desired by Customer is not already available at the Point of Delivery, additional
charges and special contract arrangements between Company and Customer may be required prior to
service being furnished.
Monthly Rate
Customer's bill will be calculated by adding the following Customer and MMBtu charges to the amounts
and quantities due under the riders listed below:
Charge Amount
Customer Charge per Meter $ 1,014.50 per month
First 0 MMBtu to 1,500 MMBtu $0.4157 per MMBtu
Next 3,500 MMBtu $0.3044 per MMBtu
All MMBtu over 5,000 MMBtu $0.0653 per MMBtu
Upstream Transportation Cost Recovery: Plus an amount for upstream transportation costs in
accordance with Part(b) of Rider GCR.
Retention Adjustment: Plus a quantity of gas as calculated in accordance with Rider RA.
Franchise Fee Adjustment: Plus an amount for franchise fees calculated in accordance with Rider
FF. Rider FF is only applicable to customers inside the corporate limits of any incorporated
municipality.
Tax Adjustment: Plus an amount for tax calculated in accordance with Rider TAX.
Surcharges: Plus an amount for surcharges calculated in accordance with the applicable rider(s).
Imbalance Fees
All fees charged to Customer under this Rate Schedule will be charged based on the quantities
determined under the applicable Transportation Agreement and quantities will not be aggregated for any
Customer with multiple Transportation Agreements for the purposes of such fees.
Monthly Imbalance Fees
Customer shall pay Company the greater of(i) $0.10 per MMBtu, or(ii) 150% of the difference per MMBtu
between the highest and lowest "midpoint" price for the Katy point listed in Platts Gas Daily in the table
entitled "Daily Price Survey" during such month, for the MMBtu of Customer's monthly Cumulative
Imbalance, as defined in the applicable Transportation Agreement. at the end of each month that exceeds
10%of Customer's receipt quantities for the month.
Ordinance No. 3770-9-20, Page 9
MID-TEX DIVISION RRC Tariff No:
ATMOS ENERGY CORPORATION
RATE SCHEDULE: T—TRANSPORTATION
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 PAGE:
Curtailment Overpull Fee
Upon notification by Company of an event of curtailment or interruption of Customer's deliveries,
Customer will, for each MMBtu delivered in excess of the stated level of curtailment or interruption, pay
Company 200% of the midpoint price for the Katy point listed in Platts Gas Daily published for the
applicable Gas Day in the table entitled "Daily Price Survey."
Replacement Index
In the event the "midpoint" or "common" price for the Katy point listed in Platts Gas Daily in the table
entitled "Daily Price Survey" is no longer published, Company will calculate the applicable imbalance fees
utilizing a daily price index recognized as authoritative by the natural gas industry and most closely
approximating the applicable index.
Agreement
A transportation agreement is required.
Notice
Service hereunder and the rates for services provided are subject to the orders of regulatory bodies
having jurisdiction and to the Company's Tariff for Gas Service.
Special Conditions
In order to receive service under Rate T, customer must have the type of meter required by Company.
Customer must pay Company all costs associated with the acquisition and installation of the meter.
Ordinance No. 3770-9-20, Page 10
MID-TEX DIVISION
ATMOS ENERGY CORPORATION
RIDER: WNA—WEATHER NORMALIZATION ADJUSTMENT
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 f PAGE:
Provisions for Adjustment
The Commodity Charge per Ccf (100 cubic feet) for gas service set forth in any Rate Schedules utilized
by the cities of the Mid-Tex Division service area for determining normalized winter period revenues shall
be adjusted by an amount hereinafter described, which amount is referred to as the "Weather
Normalization Adjustment." The Weather Normalization Adjustment shall apply to all temperature
sensitive residential and commercial bills based on meters read during the revenue months of November
through April. The five regional weather stations are Abilene, Austin, Dallas,Waco, and Wichita Falls.
Computation of Weather Normalization Adjustment
The Weather Normalization Adjustment Factor shall be computed to the nearest one-hundredth cent
per Ccf by the following formula:
(HSFi x (NDD-ADD) )
WNAFi = Ri
(BL1 + (HSFi x ADD) )
Where
i = any particular Rate Schedule or billing classification within any such
particular Rate Schedule that contains more than one billing classification
WNAFi = Weather Normalization Adjustment Factor for the ith rate schedule or
classification expressed in cents per Ccf
Ri = Commodity Charge rate of temperature sensitive sales for the ith schedule or
classification.
HSFi = heat sensitive factor for the ith schedule or classification divided by the
average bill count in that class
NDD = billing cycle normal heating degree days calculated as the simple ten-year
average of actual heating degree days.
ADD = billing cycle actual heating degree days.
Bli = base load sales for the ith schedule or classification divided by the average
bill count in that class
The Weather Normalization Adjustment for the jth customer in ith rate schedule is computed as:
WNA,= WNAF, x qy
Where q;; is the relevant sales quantity for the jth customer in ith rate schedule.
Ordinance No. 3770-9-20, Page 11
MID-TEX DIVISION
ATMOS ENERGY CORPORATION
RIDER: WNA—WEATHER NORMALIZATION ADJUSTMENT
APPLICABLE TO: ALL CUSTOMERS IN THE MID-TEX DIVISION UNDER THE RRM TARIFF
EFFECTIVE DATE: Bills Rendered on or after 12/01/2020 I PAGE:
Base Use/Heat Use Factors
Residential Commercial
Base use Heat use Base use Heat use
Weather Station Ccf CcflHDD Ccf Ccf/HDD
Abilene 10.73 0.1545 94.79 0.7284
Austin 9.53 0.1489 211.76 0.9405
Dallas 15.77 0.1792 199.74 0.9385
Waco 9.99 0.1341 145.27 0.7110
Wichita 11.61 0.1402 120.34 0.5747
Falls
Weather Normalization Adjustment(WNA) Report
On or before June 1 of each year, the company posts on its website at atmosenergy.com/mtx-wna, in
Excel format, a Weather Normalization Adjustment (WNA) Report to show how the company calculated
its WNAs factor during the preceding winter season. Additionally, on or before June 1 of each year, the
company files one hard copy and an Excel version of the WNA Report with the Railroad Commission of
Texas' Gas Services Division, addressed to the Director of that Division.
I
Ordinance No.3770-9-20, Page 12
I
Exhibit B
to 2020 RRM Resolution or Ordinance
Mid-Tex
2020 Benchmark for Pensions
and Retiree Benefits
I
Ordinance No.3770-9-20,Page 13
ATMOS ENERGY CORP.,MID-TEX DIVISION
PENSIONS AND RETIREE MEDICAL BENEFITS FOR CITIES APPROVAL
TEST YEAR ENDING DECEMBER 31,2019
Shared Services Mid-Tex Direct
Post- Supplemental Post-
Line Pension Employment Pension Executive Benefit Employment Adjustment
No. Description Account Plan Benefit Plan Account Plan Plan Benefit Plan Total
(a) (b) (c) (d) (e) (f) (g)
Proposed Benefits Benchmark-Fiscal Year 2020 Willis Towers
1 Watson Report as adjusted(1)(2)(3) $ 3,460,135 $ 3,695,384 $ 6,132,704 $ 280,578 $ 4,992,449
2 Allocation to Mid-Tex 43.29% 43.29% 76.59% 100.00% 76.59%
Proposed Benefits Benchmark Costs Allocated to Mid-Tex(Ln 1 x Ln
3 2) $ 1,497,774 $ 1,599,605 $ 4,697,072 $ 280,578 $ 3,823,744
4 O&M and Capital Allocation Factor 100.00% 100.00°A 100.00% 100.00% 100.00%
5 Proposed Benefits Benchmark Costs to Approve(Ln 3 x Ln 4)(3) $ 1,497,774 $ 1,599,605 $ 4,697,072 $ 280,578 $ 3,823,744 $ 11,898,774
ar
6 an
7 G
8 Summary of Costs to Approve(1):
0
9 ev
10 O&M Expense Factor(WP_F-2.3, Ln 2) 79.55% 79.559/o 37.83% 11.67% 37.83% oN
11 C
rr
12
13 Total Pension Account Plan $ 1,191,410 $ 1,777,056 $ 2 968 466 ~'
14 Total Post-Employment Benefit Plan $ 1,272,412 $ 1,446,647 2,719,060 z
15 Total Supplemental Executive Benefit Plan $ 32,754 32,754 ai
16 Total(Ln 13+Ln 14+Ln 15) $ 1,191,410 $ 1,272,412 $ 1,777,056 $ 32,754 $ 1,446,647 $ 5,720,280 c
17 c
18 Notes'
19 1. Studies not applicable to Mid-Tex or Shared Services are omitted. 6-
20 2. Mid-Tex is proposing that the Fiscal Year 2020 Willis Towers Watson actuarial amounts shown on WP_F-2.3 and W P_F-2.3.1,be approved by the RRM Cities as the
21 benchmark amounts to be used to calculate the regulatory asset or liability for future periods. The benchmark amount approved by the RRM Cities for future periods
22 includes only the expense amount. The amount attributable to capital is recorded to utility plant through the overhead process as described in the CAM.
23 3. SSU amounts exclude cost centers Mich do not allocate to Mid-Tex for rate making purposes.
Exhibit C
to 2020 RRM Resolution or Ordinance
Mid-Tex 2020 Schedule for
Amortization for Regulatory Liability
Ordinance No.3770-9-20,Page 15
ATMOS ENERGY CORP., MID-TEX DIVISION
RATE BASE ADJUSTMENTS
TEST YEAR ENDING DECEMBER 31, 2019
AMORTIZATION OF REGULATORY LIABILITY
Beginning of Year End of Year
Rate Base Rate Base Corrected Balance
Line Year Ended Adjustment Annual Adjustment for December 31,
No. Dec. 31 Amount Amortization (1) Amount(2) 2017 (3)
(a) (b) (c) (d) (e)
1 2017 $ - $ 292,268,881 $ 292,268,881
2 2018 292,268,881 12,075,562 280,193,319
3 2019 280,193,319 12,085,165 268,108,155
4 2020 268,108,155 11,171,173 256,936,982
5 2021 256,936,982 11,171,173 245,765,809
6 2022 245,765,809 11,171,173 234,594,635
7 2023 234,594,635 11,171,173 223,423,462
8 2024 223,423,462 11,171,173 212,252,289
9 2025 212,252,289 11,171,173 201,081,116
10 2026 201,081,116 11,171,173 189,909,943
11 2027 189,909,943 11,171,173 178,738,770
12 2028 178,738,770 11,171,173 167,567,597
13 2029 167,567,597 11,171,173 156,396,424
14 2030 156,396,424 11,171,173 145,225,251
15 2031 145,225,251 11,171,173 134,054,077
16 2032 134,054,077 11,171,173 122,882,904
17 2033 122,882,904 11,171,173 111,711,731
18 2034 111,711,731 11,171,173 100,540,558
19 2035 100,540,558 11,171,173 89,369,385
20 2036 89.369,385 11,171,173 78,198,212
21 2037 78,198,212 11,171,173 67,027,039
22 2038 67,027,039 11,171,173 55,855,866
23 2039 55,855,866 11,171,173 44,684,692
24 2040 44,684,692 11,171,173 33,513,519
25 2041 33,513,519 11,171,173 22,342,346
26 2042 22,342,346 11,171,173 11,171,173
27 2043 11,171,173 11,171,173 (0)
28
29 Revenue Related Tax Factor 7.16% See WP_F-5.1
Revenue Related Taxes on Annual Amortization *Tax
30 Amortization $ 799,924 Factor
31 Amortization Including Revenue $ 11,971,097 Amortization +Taxes
32
33 Notes:
34 1. The annual amortization of a 26 year recovery period is based on the
35 Reverse South Georgia Method.
36 2. The Regulatory Liability is recorded to FERC Account 253, Sub Account 27909.
37 3. This is the final Mid-Tex liability balance filing the Fiscal Year 2018 tax return.
I